ZEG was established in Erbil, North of Iraq as the latest member of the Zagros group.
MINISTRY OF ELECTRICITY PROJECTS
EPC 132kV GIS Substation in Erbil Governorate
Reconductoring 132kV OHTL DC Erbil Ring Network System in Erbil Governorate
EPC 132kV Underground Cable in Erbil Governorate
EPC 33kV OH TL DC and 33kV Underground Cable in Sulaimaniyah Governorate
Wind Energy Feasibility Study in Erbil, Dohuk and Sulaimaniyah Governorates
EPC 132kV GIS Substations in ERBIL Governorate
CLIENT :
KRG – Ministry of Electricity
PROJECT DESCRIPTION :
EPC of four new 132 /33/11 kV GIS Substations in the Erbil Governorate .
SCOPE OF WORK :
Provision of Engineering, Design, Manufacturing and Supply, Installation including spare parts, storage, delivery to site, testing and commissioning, training and complete handover to MOE.
CONTRACT WORTH :
70,866,081 411.00 ID
STATUS :
Ongoing
Reconductoring of 132kV OHTL DC Erbil Ring Network System in Erbil Governorate
CLIENT :
KRG – Ministry of Electricity
PROJECT DESCRIPTION :
Reconductoring Work
SCOPE OF WORK :
he total length of lines in original contract scope was 72km with additional 3 more, totaling up to 75 km
CONTRACT WORTH :
USD 7,322,132.00
PROJECT COMPLETION :
2014
EPC 132kV Underground Cable inErbil Governorate
CLIENT :
KRG – Ministry of Electricity
PROJECT DESCRIPTION :
EPC 132kV Underground Cable in Erbil Governorate using HDD Method
SCOPE OF WORK :
Design, manufacture, factory testing deliver, installation, site testing, commissioning and training of MOE personnel for 132 kV Underground Cable using HDD method.